Coordination for Assembly
Wen Zhang, Sina Shokoohyar, Anyan Qi, Elena Katok
Manufacturing & Service Operations Management
인용
- 주제공급계약 설계 · 공급망관리
- 방법
- 현상
Problem definition: Modern assembly projects usually involve many interrelated tasks outsourced to suppliers/contractors, and the project outcome depends on all contractors’ minimum effort level. To mitigate risks in such projects, the original equipment manufacturer (OEM) often uses a risk-sharing contract, under which the payment to the contractors depends on the minimum effort level. The question of how to structure supply contracts in such settings is the focus of our study. Methodology/results: We employ gametheoretic models and behavioral experiments to analyze this problem. We show that, under the risk-sharing contract, contractors may fail to achieve the desired project effort level because they may select the least efficient secure equilibrium due to strategic uncertainty. To mitigate this coordination failure, we introduce a new information-feedback mechanism that involves informing contractors about the effort exerted by other contractors in multiple feedback periods. We fully characterize contractors’ subgame-perfect secure equilibrium strategies under the feedback mechanism and identify the minimum feedback periods to achieve the Pareto optimality. We further show that this minimum feedback period increases with the number of contractors. We finally test the mechanism in the laboratory with human subjects and find qualitative support for the model. Managerial implications: Our study delivers three main messages. Firstly, contractors may fail to coordinate under a risk-sharing contract. Secondly, the OEM should require sufficient periodic feedback among contractors throughout the project to mitigate coordination failure. Thirdly, in order to address the growing challenge of coordinating multiple contractors, the OEM should offer additional feedback periods and encourage contractors to take prompt action during earlier periods. Funding: The authors gratefully acknowledge financial support from the University of Texas at Dallas. Supplemental Material: The online appendix is available at https://doi.org/10.1287/msom.2023.0342 .
불러오는 중…
- Coordinating Project Outsourcing Through Bilateral Contract Negotiations
- Optimal Procurement Design of an Assembly Supply Chain with Information Asymmetry
- Coordinating Investment, Production, and Subcontracting
- Note on Optimal Procurement Mechanisms for Assembly
- Procurement for Assembly Under Asymmetric Information: Theory and Evidence
- Designing Supply Contracts Considering Profit Targets and Risk
- Scope Contracts to Coordinate Assortment Planning in Omnichannel Retail Supply Chains
- Optimal Procurement Mechanisms for Assembly
- Pay‐Back‐Revenue‐Sharing Contract in Coordinating Supply Chains with Random Yield
- Optimal Contract Under Asymmetric Information About Fairness
아직 이 논문을 인용한 탑저널 논문이 없습니다.
15 / 42편
- Effort, Revenue, and Cost Sharing Mechanisms for Collaborative New Product Development
- Competition and Cooperation in Decentralized Push and Pull Assembly Systems
- Decentralized Pricing and Capacity Decisions in a Multitier System with Modular Assembly
- Project Management Contracts with Delayed Payments
- Aligning Capacity Decisions in Supply Chains When Demand Forecasts Are Private Information: Theory and Experiment
- Incentive Contracts in Serial Stochastic Projects
- Flexibility in Long-Term Relationships: An Experimental Study
- To Communicate or Not? Interfirm Communication in Collaborative Projects
- Incentives and Gaming in Collaborative Projects Under Risk-Sharing Partnerships
- Nonbinding Goals in Teams: A Real Effort Coordination Experiment
- 탑저널 밖 논문
- 탑저널 밖 논문
- 탑저널 밖 논문
- 탑저널 밖 논문
- 탑저널 밖 논문
- 저널Manufacturing & Service Operations Management · 27(6) · 1905–1922
- 토픽Assembly Line Balancing Optimization · Industrial and Manufacturing Engineering
- DOI10.1287/msom.2023.0342
- 저자Wen Zhang, Sina Shokoohyar, Anyan Qi, Elena Katok