Note—A Note on “Efficiency of the Antithetic Variate Method for Simulating Stochastic Networks”
인용
9
피인용
2.0
FWCI
1
IS/마케팅/OM 탑저널 피인용
2
IS/마케팅/OM 탑저널 참고문헌
- 주제시뮬레이션 기법 · 의사결정분석
01Abstract
In a recent paper by Sullivan, Hayya, and Schaul (Sullivan, R. S., J. C. Hayya, R. Schaul. 1982. Efficiency of the antithetic variate method for simulating stochastic networks. Management Sci. 28 (5, May) 563–572.), they present a theorem which proves that negative covariance will be guaranteed, and thus a variance reduction achieved, when estimating the project completion time in PERT networks using antithetic sampling procedures. Their proof is restricted to stochastic networks in which the arc time distributions are symmetric about their means. In this note we present a proof which guarantees a variance reduction for arbitrary arc time distributions.
02연구 흐름
불러오는 중…
03비슷한 논문
- Efficiency of the Antithetic Variate Method for Simulating Stochastic Networks
- Antithetic Variates, Multivariate Dependence and Simulation of Stochastic Systems
- Antithetic Variates, Common Random Numbers and Optimal Computer Time Allocation in Simulation
- Efficient Estimation of Arc Criticalities in Stochastic Activity Networks
- Overconservativeness of Variance-Based Efficiency Criteria and Probabilistic Efficiency in Rare-Event Simulation
- Strategies for Combining Antithetic Variates and Control Variates in Designed Simulation Experiments
- Conditional Monte Carlo: A Simulation Technique for Stochastic Network Analysis
- Bias in Pert Project Completion Time Calculations for a Real Network
- Virtual Measures: A Variance Reduction Technique for Simulation
- Better Estimation of PERT Activity Time Parameters
04이후 연구
05선행 연구
06서지 정보
- 저널Management Science · 29(3) · 381–384
- 토픽Resource-Constrained Project Scheduling · Management Science and Operations Research
- DOI10.1287/mnsc.29.3.381
- 저자Floyd H. Grant