A Dynamic Programming Approach to Stochastic Assembly Line Balancing
Management Science
- 주제작업장 일정 최적화 · 생산·최적화
Consider the problem of minimizing the required number of work stations on an assembly line for a given cycle time when the processing times are independent, normally distributed random variables. The assignment of tasks to stations is subject to precedence conditions, caused by technological constraints, and a lower bound on the probability of the work at any station being completed within the cycle time. We present two dynamic programming (DP) algorithms for this problem, each guaranteed to be optimal under a certain mild condition. Our general approach is based on the Held et al. (Held, M., R. M. Karp, R. Shareshian. 1963. Assembly-line-balancing-dynamic programming with precedence constraints. Oper. Res. 11 442–459.) formulation of the deterministic line balancing problem and thus represents a modification of previous work by Kao (Kao, E. P. C. 1976. A preference order dynamic program for stochastic assembly line balancing. Management Sci. 22 1097–1104.). Computational results indicate that both algorithms significantly outperform an alternative DP approach suggested by Henig (Henig, M. I. 1986. Extensions of the dynamic programming method in the deterministic and stochastic assembly-line balancing problems. Comput. Oper. Res. 13 443–449.).
불러오는 중…
불러오는 중…
불러오는 중…
불러오는 중…
- 저널Management Science · 35(4) · 459–471
- 토픽Assembly Line Balancing Optimization · Industrial and Manufacturing Engineering
- DOI10.1287/mnsc.35.4.459
- 저자Robert L. Carraway