Some Heuristics for Scheduling Jobs on Parallel Machines with Setups
Management Science
66
피인용
7.9
FWCI
3
IS/마케팅/OM 탑저널 피인용
3
IS/마케팅/OM 탑저널 참고문헌
- 주제작업장 일정 최적화 · 생산·최적화
01Abstract
This paper studies the problem of scheduling jobs on parallel machines with setup times. When a machine switches from processing one type of job to another type, setup times are incurred. The problem is to find a feasible schedule for each machine which maximizes the total reward. We study three heuristics for solving this problem. Analytical and empirical results of the heuristics are given.