Work Stretch Properties for the Scheduling of Continuous Operations Under Alternative Labor Policies
Management Science
17
피인용
2.0
FWCI
2
IS/마케팅/OM 탑저널 피인용
3
IS/마케팅/OM 탑저널 참고문헌
- 주제작업장 일정 최적화 · 생산·최적화
01Abstract
For a seven-day's-a-week operation in which N employees are needed on each weekday and n on each weekend day, with N at least as large as n, the work stretch is developed for each of several different rest policies. The work stretch is the number of consecutive work days between rest days. Additionally, work force size formulas are developed for policies not previously covered in the literature.