Managing material shortages in project supply chains: Inventories, time buffers, and supplier flexibility
Panos Kouvelis, Xingxing Chen, Yu Xia
Production and Operations Management
인용
- 주제공급계약 설계 · 공급망관리
- 방법
- 현상
We consider a two‐stage project supply chain with a downstream project firm producing an engineer‐to‐order (ETO) complex product or a make‐to‐order (MTO), low‐volume, customized industrial product as a project, and an upstream contract supplier supplying a key material to the project. The project faces two uncertainties: project activity time uncertainty and material consumption uncertainty, which may be positively or negatively correlated. In anticipation of these uncertainties, the project firm has to carefully decide its promised project due date to its project customer, against which harsh penalties will be assessed, and his material order quantity to commit to the contract supplier in advance. In most practical settings, project firms order from contracted suppliers via a flexible wholesale price contract consisting of a discounted advance order price and a risk‐premium adjusted expedite order price. The discounted advance order price encourages the project firm to take more inventory risk in the supply chain, and the expedite order price incentivizes the supplier to bear more inventory risk by carrying safety stock in excess of the project firm's advance material order. We formulate an optimization model that solves the project firm's project due date and material order problem, which takes into account the supplier's strategic reaction to the project firm's material order under the flexible wholesale price contract. We show that for MTO projects, risk‐sharing with suppliers on project materials is less important to the project firm, with the project firm assuming ownership of all material inventory in the channel and setting a deliberate project due date being the key. On the other hand, for ETO projects, risk‐sharing with contracted suppliers assumes critical importance. Project firms managing ETO projects should fully exploit the flexibility in the material supply contract to optimally drive the supplier's safety stock level and set the project due date reflecting the shared risk in the supply chain.
불러오는 중…
- Incentive Alignment and Coordination of Project Supply Chains
- Supply Chain Contracting in Environments with Volatile Input Prices and Frictions
- Flexible and Risk-Sharing Supply Contracts Under Price Uncertainty
- An Inventory Model Embedded in Designing a Supply Contract
- Multi‐Stage Supply Chain with Production Uncertainty
- Diversification Under Supply Uncertainty
- On Optimal Expediting Policy for Supply Systems with Uncertain Lead‐Times
- Increasing Supply Chain Robustness through Process Flexibility and Inventory
- Optimal Component Stocking Policy for Assemble-to-Order Systems with Lead-Time-Dependent Component and Product Pricing
- Inventory Management with Advance Demand Information and Flexible Delivery
15 / 28편
- The Value of Information Sharing in a Two-Level Supply Chain
- The Allocation of Inventory Risk in a Supply Chain: Push, Pull, and Advance-Purchase Discount Contracts
- Push, Pull, or Both? A Behavioral Study of How the Allocation of Inventory Risk Affects Channel Efficiency
- Project Management Contracts with Delayed Payments
- The Comparison of Two Vertical Outsourcing Structures under Push and Pull Contracts
- Oversight and Efficiency in Public Projects: A Regression Discontinuity Analysis
- Incentive Alignment and Coordination of Project Supply Chains
- Using Advance Purchase Discount Contracts under Uncertain Information Acquisition Cost
- 탑저널 밖 논문
- 탑저널 밖 논문
- 탑저널 밖 논문
- 탑저널 밖 논문
- 탑저널 밖 논문
- 탑저널 밖 논문
- 탑저널 밖 논문
- 저널Production and Operations Management · 32(11) · 3717–3735
- 토픽Supply Chain and Inventory Management · Management Information Systems
- DOI10.1111/poms.14059
- 저자Panos Kouvelis, Xingxing Chen, Yu Xia