Oversight and Efficiency in Public Projects: A Regression Discontinuity Analysis
Eduard Calvo, Ruomeng Cui, Juan Camilo Serpa
Management Science
- 주제소프트웨어 개발관리 · 디지털조직
- 방법
- 현상
In the United States, 42% of public infrastructure projects report delays or cost overruns. To mitigate this problem, regulators scrutinize project operations. We study the effect of oversight on delays and overruns with 262,857 projects spanning 71 federal agencies and 54,739 contractors. We identify our results using a federal bylaw: if the project’s budget is above a cutoff, procurement officers actively oversee the contractor’s operations; otherwise, most operational checks are waived. We find that oversight increases delays by 6.1%–13.8% and overruns by 1.4%–1.6%. We also show that oversight is most obstructive when the contractor has no experience in public projects, is paid with a fixed-fee contract with performance-based incentives, or performs a labor-intensive task. Oversight is least obstructive—or even beneficial—when the contractor is experienced, paid with a time-and-materials contract, or conducts a machine-intensive task. This paper was accepted by Serguei Netessine, operations management.
불러오는 중…
불러오는 중…
불러오는 중…
불러오는 중…
- 저널Management Science · 65(12) · 5651–5675
- 토픽Public Procurement and Policy · Strategy and Management
- DOI10.1287/mnsc.2018.3202
- 저자Eduard Calvo, Ruomeng Cui, Juan Camilo Serpa