Integrated Sequencing and Scheduling in Coil Coating
Wiebke Höhn, Felix G. König, Rolf H. Möhring, Marco E. Lübbecke
인용
- 주제생산 계획과 일정 · 생산·최적화
We consider a complex planning problem in integrated steel production. A sequence of coils of sheet metal needs to be color coated in consecutive stages. Different coil geometries and changes of colors necessitate time-consuming setup work. In most coating stages one can choose between two parallel color tanks. This can either reduce the number of setups needed or enable setups concurrent with production. A production plan comprises the sequencing of coils and the scheduling of color tanks and setup work. The aim is to minimize the makespan for a given set of coils. We present an optimization model for this integrated sequencing and scheduling problem. A core component is a graph theoretical model for concurrent setup scheduling. It is instrumental for building a fast heuristic that is embedded into a genetic algorithm to solve the sequencing problem. The quality of our solutions is evaluated via an integer program based on a combinatorial relaxation, showing that our solutions are within 10% of the optimum. Our algorithm is implemented at Salzgitter Flachstahl GmbH, a major German steel producer. This has led to an average reduction in makespan by over 13% and has greatly exceeded expectations. This paper was accepted by Dimitris Bertsimas, optimization.
불러오는 중…
- A Production Scheduling Problem with Sequencing Considerations
- Sequencing to Minimize Work Overload in Assembly Lines with Product Options
- A Mathematical Programming Approach to Schedule Master Slab Casters in the Steel Industry
- The Pit Charging Problem in Steel Production
- Integrated Scheduling of Production and Distribution Operations
- An Integrated Model for Job-Shop Planning and Scheduling
- A Heuristic Programming Solution to a Nonlinear Cutting Stock Problem
- A Linear Programming Model of Integrated Iron and Steel Production
- Lotsizing and Scheduling on Parallel Machines with Sequence-Dependent Setup Costs
- Production and Sales Planning with Limited Shared Tooling at the Key Operation
15 / 27편
- 탑저널 밖 논문
- 탑저널 밖 논문
- 탑저널 밖 논문
- 탑저널 밖 논문
- 탑저널 밖 논문
- 탑저널 밖 논문
- 탑저널 밖 논문
- 탑저널 밖 논문
- 탑저널 밖 논문
- 탑저널 밖 논문
- 탑저널 밖 논문
- 탑저널 밖 논문
- 탑저널 밖 논문
- 탑저널 밖 논문
- 탑저널 밖 논문
- 저널Management Science · 57(4) · 647–666
- 토픽Scheduling and Optimization Algorithms · Industrial and Manufacturing Engineering
- DOI10.1287/mnsc.1100.1302
- 저자Wiebke Höhn, Felix G. König, Rolf H. Möhring, Marco E. Lübbecke