- 주제생산 계획과 일정 · 생산·최적화
01Abstract
This paper investigates the problem of sequencing N products on an assembly line with two objectives: minimizing (1) the risk of conveyor stoppage and (2) the total utility work. For a single station with arbitrary processing times, this problem is proved NP-hard in the strong sense for each of the two objectives. For a single station with two product types, each of which has a constant processing time, a sequence minimizing both objectives can be found in O(log N) computation time.
02연구 흐름
불러오는 중…
03비슷한 논문
- Sequencing to Minimize Work Overload in Assembly Lines with Product Options
- Sequencing JIT Mixed-Model Assembly Lines Under Station-Load and Part-Usage Constraints
- Lot Sizing and Sequencing for <i>N</i> Products on One Facility
- Sequencing Operations to Minimize In-Process Inventory Costs
- Note—Sequencing JIT Mixed-Model Assembly Lines
- Batching to Minimize Flow Times on One Machine
- Level Schedules for Mixed-Model Assembly Lines in Just-In-Time Production Systems
- Line Balancing-Sequencing for Mixed-Model Assembly
- Balancing Mixed Model Lines with In-Process Inventories
- Computer Simulation for Mixed-Model Production Lines
04이후 연구
05선행 연구
06서지 정보
- 저널Management Science · 41(3) · 485–495
- 토픽Assembly Line Balancing Optimization · Industrial and Manufacturing Engineering
- DOI10.1287/mnsc.41.3.485
- 저자Li-Hui Tsai