A Fast Taboo Search Algorithm for the Job Shop Problem
Eugeniusz Nowicki, Czesław Smutnicki
인용
983
피인용
66.7
FWCI
3
IS/마케팅/OM 탑저널 피인용
0
IS/마케팅/OM 탑저널 참고문헌
- 주제작업장 일정 최적화 · 생산·최적화
01Abstract
A fast and easily implementable approximation algorithm for the problem of finding a minimum makespan in a job shop is presented. The algorithm is based on a taboo search technique with a specific neighborhood definition which employs a critical path and blocks of operations notions. Computational experiments (up to 2,000 operations) show that the algorithm not only finds shorter makespans than the best approximation approaches but also runs in shorter time. It solves the well-known 10 × 10 hard benchmark problem within 30 seconds on a personal computer.
02연구 흐름
불러오는 중…
03비슷한 논문
- The Shifting Bottleneck Procedure for Job Shop Scheduling
- An Algorithm for Solving the Job-Shop Problem
- Job-Shop Scheduling by Implicit Enumeration
- Scheduling the General Job-Shop
- New Search Spaces for Sequencing Problems with Application to Job Shop Scheduling
- Minimizing the Makespan in the 3-Machine Assembly-Type Flowshop Scheduling Problem
- The One-Machine Problem with Delayed Precedence Constraints and its Use in Job Shop Scheduling
- Heuristics in Job Shop Scheduling
- Note. Satisfying Due Dates in Large Job Shops
- A Broader View of the Job-Shop Scheduling Problem
04이후 연구
05선행 연구
참고문헌 정보가 아직 없습니다. 최근 논문은 OpenAlex에 참고문헌이 늦게 들어오며, 들어오면 매주 갱신 때 반영됩니다.
06서지 정보
- 저널Management Science · 42(6) · 797–813
- 토픽Scheduling and Optimization Algorithms · Industrial and Manufacturing Engineering
- DOI10.1287/mnsc.42.6.797
- 저자Eugeniusz Nowicki, Czesław Smutnicki