Minimizing Makespan with Bimodal Processing Time Distributions
Management Science
2
피인용
1.8
FWCI
0
IS/마케팅/OM 탑저널 피인용
4
IS/마케팅/OM 탑저널 참고문헌
- 주제작업장 일정 최적화 · 생산·최적화
01Abstract
We consider the problem of scheduling n tasks on two identical parallel processors. Task i has a processing time of one time unit, but might have to undergo processing for a second time unit with probability p i , i.e., the processing time distributions of the tasks have mass only on one and on two. We are interested in the sequence in which to process these tasks in order to minimize the expected completion time of all tasks. The optimal sequence turns out to be a sequence not well-known in the theory of scheduling.