Approximating the Criticality Indices of the Activities in PERT Networks
Bajis M. Dodin, Salah E. Elmaghraby
인용
- 주제네트워크 흐름 최적화 · 생산·최적화
A stochastic PERT network is a directed acyclic network in which the arc lengths are independent random variables with known distributions. A fundamental problem in PERT networks is to identify the activities which are critical to the achievement of the project objectives. In an activity network if the duration of each activity is not a random variable, then it is easy to identify the criticality of each activity represented by its float time. However, when the duration of any activity is a random variable, it is not easy to identify the criticality of each activity. In this case the criticality of an activity is known as the “criticality index,” which is defined as the sum of the criticality indices of the paths containing it. The criticality index of a path is the probability that the duration of the path is greater than or equal to the duration of every other path in the network. Clearly, the criticality index of an activity can be obtained by determining the criticality indices of the paths, which requires identifying all the paths, determining their criticality indices, then identifying the paths containing the activity. In this paper we develop a theory which leads to a procedure to approximate the criticality indices of all the activities without going through the above three steps. The procedure has been applied to large size PERT networks generated at random, and the results are found to be very close to those obtained by extensive Monte Carlo sampling.
불러오는 중…
- On the Expected Duration of PERT Type Networks
- A Statistical Theory for PERT Critical Path Analysis
- Better Estimation of PERT Activity Time Parameters
- A Statistical Theory for Pert in Which Completion Times of Activities are Inter-Dependent
- Efficient Estimation of Arc Criticalities in Stochastic Activity Networks
- Numerical Operators for Statistical PERT Critical Path Analysis
- Bayesian Point Estimation and the PERT Scheduling of Stochastic Activities
- Resource Allocation in a PERT Network Under Continuous Activity Time-Cost Functions
- Another Look at the PERT Assumptions
- Bias in Pert Project Completion Time Calculations for a Real Network
아직 이 논문을 인용한 탑저널 논문이 없습니다.
- 탑저널 밖 논문
- 탑저널 밖 논문
- 탑저널 밖 논문
- 탑저널 밖 논문
- 탑저널 밖 논문
- 저널Management Science · 31(2) · 207–223
- 토픽Resource-Constrained Project Scheduling · Management Science and Operations Research
- DOI10.1287/mnsc.31.2.207
- 저자Bajis M. Dodin, Salah E. Elmaghraby