Scheduling with Deadlines and Loss Functions

Robert McNaughton

Management Science

845
피인용
11.3
FWCI
17
IS/마케팅/OM 탑저널 피인용
0
IS/마케팅/OM 탑저널 참고문헌
01Abstract

The problem of this paper is that of scheduling several one-stage tasks on several processors, which are capable of handling the tasks with varying degrees of efficiency, to minimize the total loss, which is a sum of losses associated with the individual tasks. Each task has a deadline; the individual loss associated with it is a function of amount of time between the deadline and the time of completion if the former precedes the latter, and zero otherwise.