Multiproject Scheduling with Limited Resources: A Zero-One Programming Approach

A. Alan B. Pritsker, Lawrence J. Waiters, Philip M. Wolfe

Management Science

744
피인용
5.3
FWCI
13
IS/마케팅/OM 탑저널 피인용
19
IS/마케팅/OM 탑저널 참고문헌
01Abstract

A zero-one (0-1) linear programming formulation of multiproject and job-shop scheduling problems is presented that is more general and computationally tractable than other known formulations. It can accommodate a wide range of real-world situations including multiple resource constraints, due dates, job splitting, resource, substitutability, and concurrency and nonconcurrency of job performance requirements. Three possible objective functions are discussed; minimizing total throughput time for all projects: minimizing the time by which all projects are completed (i.e., minimizing makespan); and minimizing total lateness or lateness penalty for all projects.