Note—Sequencing <i>n</i> Jobs on <i>m</i> Machines to Minimise Maximum Tardiness: A Branch-and-Bound Solution
Management Science
43
피인용
4.0
FWCI
0
IS/마케팅/OM 탑저널 피인용
6
IS/마케팅/OM 탑저널 참고문헌
- 주제작업장 일정 최적화 · 생산·최적화
01Abstract
Each of n jobs is to be sequenced on m machines, with each job having a due date, and we wish to minimise the maximum tardiness of any job. The problem has been solved by Smith [Smith, W. E. 1956. Various optimizers for single-state production. Naval Research Logistics Quarterly 3 59–66] for the case of one machine. This note develops a branch-and-bound method for the general case.