Note—Sequencing with Finite Intermediate Storage
Management Science
14
피인용
0.0
FWCI
0
IS/마케팅/OM 탑저널 피인용
5
IS/마케팅/OM 탑저널 참고문헌
- 주제작업장 일정 최적화 · 생산·최적화
01Abstract
This note presents procedures for finding optimal solutions to the deterministic N-job two machine flow-shop sequencing problem when the buffer size z is nearly the same as the number of jobs. When m = N − z − 2 is small, a simple and fast procedure that uses Johnson's algorithm on the middle N − 2m jobs is used. The procedure has a computational complexity of o(N 2m+1 ) comparisons.
02연구 흐름
불러오는 중…
03비슷한 논문
불러오는 중…
04이후 연구
불러오는 중…
05선행 연구
불러오는 중…
06서지 정보
- 저널Management Science · 23(2) · 216–217
- 토픽Scheduling and Optimization Algorithms · Industrial and Manufacturing Engineering
- DOI10.1287/mnsc.23.2.216
- 저자S. S. Reddi