This note presents procedures for finding optimal solutions to the deterministic N-job two machine flow-shop sequencing problem when the buffer size z is nearly the same as the number of jobs. When m = N − z − 2 is small, a simple and fast procedure that uses Johnson's algorithm on the middle N − 2m jobs is used. The procedure has a computational complexity of o(N2m+1) comparisons.
02연구 흐름
불러오는 중…
03비슷한 논문
- Sequencing Two-Machine Flow-Shops with Finite Intermediate Storage
- A Heuristic Algorithm for the <i>n</i> Job, <i>m</i> Machine Sequencing Problem
- <i>N</i>-Job, One Machine Sequencing Problems Under Uncertainty
- Note—Sequencing <i>n</i> Jobs on <i>m</i> Machines to Minimise Maximum Tardiness: A Branch-and-Bound Solution
- Note—On the Sequencing of <i>n</i> Jobs on One Machine to Minimize the Number of Jobs Late
- The Sequencing Problem
- An <i>n</i> Job, One Machine Sequencing Algorithm for Minimizing the Number of Late Jobs
- Batching to Minimize Flow Times on One Machine
- Job Shop Sequencing Problem on Two Machines with Time Lag Constraints
- Discussion: Sequencing <i>n</i> Jobs on Two Machines with Arbitrary Time Lags
04이후 연구
아직 이 논문을 인용한 탑저널 논문이 없습니다.
05선행 연구
- Sequencing Two-Machine Flow-Shops with Finite Intermediate Storage
- 탑저널 밖 논문
- 탑저널 밖 논문
- 탑저널 밖 논문
- 탑저널 밖 논문
06서지 정보
- 저널Management Science · 23(2) · 216–217
- 토픽Scheduling and Optimization Algorithms · Industrial and Manufacturing Engineering
- DOI10.1287/mnsc.23.2.216
- 저자S. S. Reddi