Job Shop Sequencing Problem on Two Machines with Time Lag Constraints

S. S. Panwalkar

Management Science

2
피인용
0.0
FWCI
0
IS/마케팅/OM 탑저널 피인용
3
IS/마케팅/OM 탑저널 참고문헌
01Abstract

The problem studied is that of two-machine job shop sequencing where some jobs are processed first on machine 1 and then on machine 2, while the remaining jobs are processed in the reverse order. The objective is to determine an ordered sequence which minimizes the total processing time, subject to some specified lag time constraints. A rule is given for determining two different sequences for the two machines which represent an optimal solution.