Scheduling a Project to Maximize Its Present Value: A Zero-One Programming Approach

Robert H. Doersch, J. Herbert Patterson

Management Science

147
피인용
0.8
FWCI
4
IS/마케팅/OM 탑저널 피인용
7
IS/마케팅/OM 탑저널 참고문헌
01Abstract

A zero-one integer programming formulation of the project scheduling problem is reported which maximizes the discounted value of cash flows in a project when progress payments and cash outflows are made upon the completion of certain activities. While this problem has been treated previously, it has not been addressed in a manner which allows for the type of constraints treated in this paper. And while cash can be treated as any other resource in the noncash flow, resource-constrained version of this problem, the effects of cash inflows and outflows and the time sequencing alternatives for them allow for a different treatment of cash resources than has been previously reported.