Scheduling a Project to Maximize Its Present Value: A Zero-One Programming Approach
Robert H. Doersch, J. Herbert Patterson
Management Science
- 주제불확실성하 투자 · 생산·최적화
A zero-one integer programming formulation of the project scheduling problem is reported which maximizes the discounted value of cash flows in a project when progress payments and cash outflows are made upon the completion of certain activities. While this problem has been treated previously, it has not been addressed in a manner which allows for the type of constraints treated in this paper. And while cash can be treated as any other resource in the noncash flow, resource-constrained version of this problem, the effects of cash inflows and outflows and the time sequencing alternatives for them allow for a different treatment of cash resources than has been previously reported.
불러오는 중…
불러오는 중…
불러오는 중…
불러오는 중…
- 저널Management Science · 23(8) · 882–889
- 토픽Resource-Constrained Project Scheduling · Management Science and Operations Research
- DOI10.1287/mnsc.23.8.882
- 저자Robert H. Doersch, J. Herbert Patterson