A Branch and Bound Procedure for the Resource Constrained Project Scheduling Problem with Discounted Cash Flows
인용
- 주제작업장 일정 최적화 · 생산·최적화
Management of projects is complicated by the scarcity of resources required to execute them. Limited resources usually extend the project completion times beyond those determined by CPM/PERT. Several solution procedures have been developed for solving the resource constrained project scheduling problem. One objective commonly used for these problems is to complete the project as early as possible (minimize makespan). The problem considered in this paper is a resource constrained project scheduling problem, with the added features that there are cash flows associated with the project activities, and the objective is to schedule the project activities in such a way that the net present value of cash flows is maximized. With these features the problem becomes financially motivated and more realistic. We introduce a branch and bound procedure to solve the resource constrained project scheduling problem with discounted cash flows. Our procedure exploits the known fact that potential resource violations can be eliminated by introducing additional precedence relations between certain project activities. Specifically, we use the “minimal delaying alternatives” concept to resolve resource conflicts. The bounds in the branch and bound procedure are computed by solving Payment Scheduling Problems, which can be formulated as linear programs and by that are well-solvable. We test our procedure computationally on a set of 90 test problems from the literature and compare it with the only other exact procedure we know of.
불러오는 중…
- A Branch-and-Bound Procedure for the Multiple Resource-Constrained Project Scheduling Problem
- A Branch and Bound Algorithm for Minimizing Cost in Project Scheduling
- On Maximizing the Net Present Value of a Project Under Renewable Resource Constraints
- A Time-Oriented Branch-and-Bound Algorithm for Resource-Constrained Project Scheduling with Generalised Precedence Constraints
- A Comparison of Exact Approaches for Solving the Multiple Constrained Resource, Project Scheduling Problem
- An Exact Algorithm for the Resource-Constrained Project Scheduling Problem Based on a New Mathematical Formulation
- New Benchmark Results for the Resource-Constrained Project Scheduling Problem
- Comparison of a Multi-Pass Heuristic Decomposition Procedure with Other Resource-Constrained Project Scheduling Procedures
- Resource-Constrained Project Scheduling with Time-Resource Tradeoffs: The Nonpreemptive Case
- Scheduling Resource-Constrained Projects Competitively at Modest Memory Requirements
- An Efficient Integer Programming Algorithm with Network Cuts for Solving Resource-Constrained Scheduling Problems
- A Comparison of Exact Approaches for Solving the Multiple Constrained Resource, Project Scheduling Problem
- An Algorithm for Optimal Project Scheduling under Multiple Resource Constraints
- Scheduling a Project to Maximize Its Present Value: A Zero-One Programming Approach
- A Comparison of Heuristics for Scheduling Projects with Cash Flows and Resource Restrictions
- 탑저널 밖 논문
- 탑저널 밖 논문
- 탑저널 밖 논문
- 탑저널 밖 논문
- 탑저널 밖 논문
- 탑저널 밖 논문
- 저널Management Science · 42(10) · 1395–1408
- 토픽Resource-Constrained Project Scheduling · Management Science and Operations Research
- DOI10.1287/mnsc.42.10.1395
- 저자Oya Icmeli, Ş. Selçuk Erengüç