A Comparison of Heuristics for Scheduling Projects with Cash Flows and Resource Restrictions
Management Science
135
피인용
3.2
FWCI
3
IS/마케팅/OM 탑저널 피인용
9
IS/마케팅/OM 탑저널 참고문헌
- 주제작업장 일정 최적화 · 생산·최적화
01Abstract
The problem addressed in this paper is the scheduling of activities in a project to maximize net present value given cash inflows, outflows, and resource restrictions. Although optimization procedures exist for small problems of this type, they generally cannot solve large-scale problems and may not be widely available. Six heuristic scheduling rules are compared on 80 test problems. The test problems include large-scale engineering construction projects as well as 50 resource constrained problems from the literature.
02연구 흐름
불러오는 중…
03비슷한 논문
불러오는 중…
04이후 연구
불러오는 중…
05선행 연구
불러오는 중…
06서지 정보
- 저널Management Science · 32(10) · 1291–1300
- 토픽Resource-Constrained Project Scheduling · Management Science and Operations Research
- DOI10.1287/mnsc.32.10.1291
- 저자Robert A. Russell