A Comparison of Heuristics for Scheduling Projects with Cash Flows and Resource Restrictions
인용
135
피인용
3.1
FWCI
3
IS/마케팅/OM 탑저널 피인용
9
IS/마케팅/OM 탑저널 참고문헌
- 주제작업장 일정 최적화 · 생산·최적화
01Abstract
The problem addressed in this paper is the scheduling of activities in a project to maximize net present value given cash inflows, outflows, and resource restrictions. Although optimization procedures exist for small problems of this type, they generally cannot solve large-scale problems and may not be widely available. Six heuristic scheduling rules are compared on 80 test problems. The test problems include large-scale engineering construction projects as well as 50 resource constrained problems from the literature.
02연구 흐름
불러오는 중…
03비슷한 논문
- A Comparison of Heuristic and Optimum Solutions in Resource-Constrained Project Scheduling
- Heuristics for Scheduling Resource-Constrained Projects: An Experimental Investigation
- A Heuristic Model for Scheduling Large Projects with Limited Resources
- Multi-Project Scheduling: Categorization of Heuristic Rules Performance
- Comparison of a Multi-Pass Heuristic Decomposition Procedure with Other Resource-Constrained Project Scheduling Procedures
- Heuristic Scheduling of Activities under Resource and Precedence Restrictions
- A Comparison of Exact Approaches for Solving the Multiple Constrained Resource, Project Scheduling Problem
- A Branch and Bound Procedure for the Resource Constrained Project Scheduling Problem with Discounted Cash Flows
- On Maximizing the Net Present Value of a Project Under Renewable Resource Constraints
- Scheduling a Project to Maximize Its Present Value: A Zero-One Programming Approach
04이후 연구
05선행 연구
- A Comparison of Heuristic and Optimum Solutions in Resource-Constrained Project Scheduling
- A Comparison of Exact Approaches for Solving the Multiple Constrained Resource, Project Scheduling Problem
- Cash Flows in Networks
- Scheduling a Project to Maximize Its Present Value: A Zero-One Programming Approach
- Multi-Project Scheduling: Categorization of Heuristic Rules Performance
- 탑저널 밖 논문
- 탑저널 밖 논문
- 탑저널 밖 논문
- 탑저널 밖 논문
06서지 정보
- 저널Management Science · 32(10) · 1291–1300
- 토픽Resource-Constrained Project Scheduling · Management Science and Operations Research
- DOI10.1287/mnsc.32.10.1291
- 저자Robert A. Russell