A Horizon-Varying, Zero-One Approach to Project Scheduling

James Herbert Patterson, Walter D. Huber

Management Science

인용
144
피인용
10.3
FWCI
8
IS/마케팅/OM 탑저널 피인용
8
IS/마케팅/OM 탑저널 참고문헌
01Abstract

Bounding techniques similar to those used with branch and bound procedures are used in this study in conjunction with zero-one programming to produce minimum duration schedules for the resource constrained, project scheduling problem. The algorithms developed consist of examining the feasibility of a series of zero-one programming problems rather than solving one zero-one problem optimally. Computational results demonstrate the advantage of this method over using zero-one programming without employing any form of bounding. A comparison with other exact procedures for solving the resource constrained, project scheduling problem is also given.