Optimum Time Compression in Project Scheduling
Leonard R. Lamberson, R. R. Hocking
Management Science
62
피인용
2.1
FWCI
1
IS/마케팅/OM 탑저널 피인용
11
IS/마케팅/OM 탑저널 참고문헌
- 주제네트워크 흐름 최적화 · 생산·최적화
01Abstract
An algorithm based on convex programming is developed for optimum time compression in network scheduling systems. The development allows for the activity time-cost trade-off functions to be any differentiable convex function. Decomposition theory is then applied to reduce the amount of computation necessary. This along with a limited number of rules to structure any incoming vector makes the algorithm amenable to time compression in large project networks.
02연구 흐름
불러오는 중…
03비슷한 논문
불러오는 중…
04이후 연구
불러오는 중…
05선행 연구
불러오는 중…
06서지 정보
- 저널Management Science · 16(10) · B–597
- 토픽Resource-Constrained Project Scheduling · Management Science and Operations Research
- DOI10.1287/mnsc.16.10.b597
- 저자Leonard R. Lamberson, R. R. Hocking