01Abstract
The degree of complexity of a critical path network may be classified by calculating a Coefficient of Network Complexity. It is defined as the quotient of activities squared divided by events or preceding work items squared divided by work items. Three distinct contributions are offered. First, the CNC may serve as an indicator of the attention spent in planning the project. Second, the CNC may be used to derive a predictor of network computer processing time. Third, the CNC value suggests the appropriate processing scheme.
02연구 흐름
불러오는 중…
03비슷한 논문
- Decomposition of Project Networks
- Approximating the Criticality Indices of the Activities in PERT Networks
- Simplification Activities in a Network Scheduling Context
- A Dynamic Programming Solution to Cost-Time Tradeoff for CPM
- A Network Flow Computation for Project Cost Curves
- The Just Noticeable Difference in Complexity of Jobs
- Critical Path Problems with Concave Cost-Time Curves
- Efficient Estimation of Arc Criticalities in Stochastic Activity Networks
- Optimum Time Compression in Project Scheduling
- Note—Comments on the Complexity Rating Factor for Layout Problems
04이후 연구
05선행 연구
- A Statistical Theory for PERT Critical Path Analysis
- The Theory of Networks and Management Science: Part II
- 탑저널 밖 논문
- 탑저널 밖 논문
- 탑저널 밖 논문
- 탑저널 밖 논문
- 탑저널 밖 논문
06서지 정보
- 저널Management Science · 21(2) · 172–177
- 토픽Resource-Constrained Project Scheduling · Management Science and Operations Research
- DOI10.1287/mnsc.21.2.172
- 저자Richard A. Kaimann