01Abstract
In this paper, we deal with the two-product, single-machine, static demand, infinite horizon lot scheduling problem. After a quick review of the literature, the necessary and sufficient conditions for feasibility are derived without imposing any preliminary requirements. Then, an optimal solution algorithm is presented. Finally, we show that a necessary condition for the feasibility of N-product schedules is that each cycle time be an integer multiple of some basic cycle time.
02연구 흐름
불러오는 중…
03비슷한 논문
- Comments on the Two-Product, Single-Machine, Static Demand, Infinite Horizon Lot Scheduling Problem
- Feasibility of Scheduling Lot Sizes of Three Products on One Machine
- On the Feasibility of Scheduling Lot Sizes for Two Products on One Machine
- Note—On the Deterministic Demand Multi-Product Single-Machine Lot Scheduling Problem
- Scheduling a Multi-Product Single Machine System for an Infinite Planning Period
- On the General Feasibility Test of Scheduling Lot Sizes for Several Products on One Machine
- An Iterative Procedure for the Single-Machine Multi-Product Lot Scheduling Problem
- Lot Size Scheduling on a Single Machine for Stochastic Demand
- Note—A Note on the Single-Machine Multi-Product Lot Scheduling Problem
- A Dynamic Programming Approach to a Lot Size Scheduling Problem
04이후 연구
05선행 연구
- A Dynamic Programming Approach to a Lot Size Scheduling Problem
- The Economic Lot Scheduling Problem (ELSP): Review and Extensions
- Scheduling a Multi-Product Single Machine System for an Infinite Planning Period
- An Iterative Procedure for the Single-Machine Multi-Product Lot Scheduling Problem
- Note—A Note on the Single-Machine Multi-Product Lot Scheduling Problem
- On the Feasibility of Scheduling Lot Sizes for Two Products on One Machine
- Production Runs for Multiple Products: The Two-Product Heuristic
- Note—On “Production Runs for Multiple Products: The Two-Product Heuristic”
- 탑저널 밖 논문
06서지 정보
- 저널Management Science · 28(7) · 798–807
- 토픽Scheduling and Optimization Algorithms · Industrial and Manufacturing Engineering
- DOI10.1287/mnsc.28.7.798
- 저자Fayez Fouad Boctor