- 주제생산 계획과 일정 · 생산·최적화
01Abstract
This paper considers the Economic Lot Scheduling Problem: that is, the problem of finding a feasible schedule that allows cyclic production of several products on a single facility so as to minimize holding and set up costs. We consider the case when three products are required to be produced in a given fixed lot size and at regular intervals. We derive a very simple test for existence of a feasible schedule and a method of constructing feasible schedules if one exists. The approach is simpler than the mixed integer programming approach and enumeration schemes currently proposed in the literature and is constructive.
02연구 흐름
불러오는 중…
03비슷한 논문
- On the Feasibility of Scheduling Lot Sizes for Two Products on One Machine
- On the General Feasibility Test of Scheduling Lot Sizes for Several Products on One Machine
- Scheduling Economic Lot Size Production Runs
- Lot Size Scheduling on a Single Machine for Stochastic Demand
- Programming of Economic Lot Sizes
- Lot Sizing and Sequencing for <i>N</i> Products on One Facility
- Economic Lot Scheduling for Multiple Products on Parallel Identical Processors
- A Computational Approach to the Economic Lot Scheduling Problem
- The Two-Product, Single-Machine, Static Demand, Infinite Horizon Lot Scheduling Problem
- An Iterative Procedure for the Single-Machine Multi-Product Lot Scheduling Problem
04이후 연구
아직 이 논문을 인용한 탑저널 논문이 없습니다.
05선행 연구
- A Dynamic Programming Approach to a Lot Size Scheduling Problem
- The Economic Lot Scheduling Problem (ELSP): Review and Extensions
- On the General Feasibility Test of Scheduling Lot Sizes for Several Products on One Machine
- On the Feasibility of Scheduling Lot Sizes for Two Products on One Machine
- 탑저널 밖 논문
- 탑저널 밖 논문
- 탑저널 밖 논문
06서지 정보
- 저널Management Science · 38(10) · 1482–1494
- 토픽Supply Chain and Inventory Management · Management Information Systems
- DOI10.1287/mnsc.38.10.1482
- 저자Celia A. Glass