New Benchmark Results for the Resource-Constrained Project Scheduling Problem
Erik Demeulemeester, Willy Herroelen
Management Science
- 주제작업장 일정 최적화 · 생산·최적화
This paper reports on new insights derived from computational results obtained with an updated version of the branch-and-bound procedure previously developed by Demeulemeester and Herroelen (Demeulemeester, E., W. Herroelen. 1992. A branch-and-bound procedure for the multiple resource-constrained project scheduling problem. Management Sci. 38 1803–1818.) for solving the resource-constrained project scheduling problem (RCPSP). The new code fully exploits the advantages of 32-bit programming provided by recent compilers running on platforms such as Windows NT ® and OS/2 ® : flat memory, increased addressable memory, and fast program execution. We study the impact of three important variables on the computation time for the RCPSP: addressable computer memory, the search strategy (depth-first, best-first, or hybrid), and the introduction of a stronger lower bound. We compare the results obtained by a truncated branch-and-bound procedure with the results generated by the minimum slack time heuristic and report on the dependency of its solution quality on the allotted CPU time.
불러오는 중…
불러오는 중…
불러오는 중…
불러오는 중…
- 저널Management Science · 43(11) · 1485–1492
- 토픽Resource-Constrained Project Scheduling · Management Science and Operations Research
- DOI10.1287/mnsc.43.11.1485
- 저자Erik Demeulemeester, Willy Herroelen