New Benchmark Results for the Resource-Constrained Project Scheduling Problem

Erik Demeulemeester, Willy Herroelen

Management Science

258
피인용
15.4
FWCI
3
IS/마케팅/OM 탑저널 피인용
20
IS/마케팅/OM 탑저널 참고문헌
01Abstract

This paper reports on new insights derived from computational results obtained with an updated version of the branch-and-bound procedure previously developed by Demeulemeester and Herroelen (Demeulemeester, E., W. Herroelen. 1992. A branch-and-bound procedure for the multiple resource-constrained project scheduling problem. Management Sci. 38 1803–1818.) for solving the resource-constrained project scheduling problem (RCPSP). The new code fully exploits the advantages of 32-bit programming provided by recent compilers running on platforms such as Windows NT ® and OS/2 ® : flat memory, increased addressable memory, and fast program execution. We study the impact of three important variables on the computation time for the RCPSP: addressable computer memory, the search strategy (depth-first, best-first, or hybrid), and the introduction of a stronger lower bound. We compare the results obtained by a truncated branch-and-bound procedure with the results generated by the minimum slack time heuristic and report on the dependency of its solution quality on the allotted CPU time.

02연구 흐름

불러오는 중…

03비슷한 논문

불러오는 중…

04이후 연구

불러오는 중…

05선행 연구

불러오는 중…

06서지 정보