Comparison of a Multi-Pass Heuristic Decomposition Procedure with Other Resource-Constrained Project Scheduling Procedures
Charles A. Holloway, Rosser T. Nelson, Vichit Suraphongschai
인용
- 주제작업장 일정 최적화 · 생산·최적화
The purpose of this paper is to evaluate a heuristic procedure for solving the resource-constrained project scheduling problem. Projects that involve completing a sequence of well defined activities, some of which can be done in parallel, often are characterized by capacity limitations on some resources. This means schedules generated using standard critical path methods often are not feasible. Resource leveling procedures have been developed to improve the schedule. Formulating the problem with explicit resource constraints is another, more direct, way to accommodate limited capacities. Solution procedures to this problem include simple, single-pass heuristics and branch-and-bound optimization procedures. The former are easy to apply but may yield poor results. The latter provide optimal results but require a substantial amount of computation even for small problems. The procedure evaluated here is representative of a class of multi-pass procedures based on problem decomposition. A brief outline of the heuristic procedure and the method of decomposition is given in the paper. It is applicable to single or multiple project networks. Comparisons were made between this procedure and single-pass heuristics and branch-and-bound procedures. Solutions found using the multi-pass procedure were comparable to those obtained with a branch-and-bound optimization algorithm while computing times were significantly shorter. Analysis based on the sample of problems tested indicates the procedure is much less sensitive to problem size than the branch-and-bound algorithm. The evaluation, consisting of testing procedures using a set of test problems, is described in detail. The overall results suggest that the method and procedure used may provide an effective means of computing schedules for resource-constrained projects.
불러오는 중…
- A Comparison of Exact Approaches for Solving the Multiple Constrained Resource, Project Scheduling Problem
- A Comparison of Heuristic and Optimum Solutions in Resource-Constrained Project Scheduling
- A Branch-and-Bound Procedure for the Multiple Resource-Constrained Project Scheduling Problem
- Heuristics for Scheduling Resource-Constrained Projects: An Experimental Investigation
- A Comparison of Heuristics for Scheduling Projects with Cash Flows and Resource Restrictions
- A Branch and Bound Procedure for the Resource Constrained Project Scheduling Problem with Discounted Cash Flows
- An Efficient Integer Programming Algorithm with Network Cuts for Solving Resource-Constrained Scheduling Problems
- A Heuristic Model for Scheduling Large Projects with Limited Resources
- An Algorithm for Optimal Project Scheduling under Multiple Resource Constraints
- Resource-Constrained Project Scheduling with Time-Resource Tradeoffs: The Nonpreemptive Case
아직 이 논문을 인용한 탑저널 논문이 없습니다.
- Multiproject Scheduling with Limited Resources: A Zero-One Programming Approach
- A Comparison of Heuristic and Optimum Solutions in Resource-Constrained Project Scheduling
- An Algorithm for Optimal Project Scheduling under Multiple Resource Constraints
- A Heuristic Model for Scheduling Large Projects with Limited Resources
- Alternative Formulation of the Job Shop Problem with Due Dates
- Job Shop Scheduling with Due Dates and Overtime Capability
- Job Shop Scheduling with Due Dates and Variable Processing Times
- 탑저널 밖 논문
- 탑저널 밖 논문
- 탑저널 밖 논문
- 탑저널 밖 논문
- 탑저널 밖 논문
- 탑저널 밖 논문
- 저널Management Science · 25(9) · 862–872
- 토픽Resource-Constrained Project Scheduling · Management Science and Operations Research
- DOI10.1287/mnsc.25.9.862
- 저자Charles A. Holloway, Rosser T. Nelson, Vichit Suraphongschai