A Comparison of Heuristic and Optimum Solutions in Resource-Constrained Project Scheduling

Edward W. Davis, J. Herbert Patterson

Management Science

457
피인용
7.9
FWCI
11
IS/마케팅/OM 탑저널 피인용
9
IS/마케팅/OM 탑저널 참고문헌
01Abstract

The problem addressed is that of scheduling the activities of a project network to minimize project duration under conditions of multiple limited resource requirements and availabilities. Various heuristic sequencing rules have been applied to this problem, and the effectiveness of these rules relative to one another has been previously compared in the literature. However, there have been no previous comparisons of the effectiveness of these rules relative to an optimum solution. This paper makes such a comparison of eight different heuristic scheduling rules, including those found most effective in previous research on this problem. Results are presented for a total of eighty-three different multi-resource problems.

02연구 흐름

불러오는 중…

03비슷한 논문

불러오는 중…

04이후 연구

불러오는 중…

05선행 연구

불러오는 중…

06서지 정보